Excavation Works of TEİAŞ Projects in Progress

DSC02343

Excavation works of 154 kV Kartal – İçmeler project has started on June 22nd and work is completed for four sections until start of August.

Likewise, excavation works of 380 kV Yeni Ambarlı – Yenibosna project has started on July 3rd. Until August 11, 1500 m, 2 sections are excavated and Brugg accessories containing 54 joints and 6 terminations are delivered to site.