HVAC Test Completed Successfully

Between 27 and 30 March, TEIAS Kucukbakkalkoy – Maltepe project’s site tests including the HVAC test, were performed.

Circuit comprising of 32 km 1x2000mm2 cable, 6 GIS terminations and 42 insulated joints was tested and fifth 380 kV of Demirer Kablo was thereby successfully completed. This was the first HVAC test performed with GIS terminations in both ends.