Demirer Kablo Awarded 132 kV Tender in IRAQ

Award letter of tender 24/NT of ETP was recieved on 18.03.2013. Works amounting 17.5 MUSD, include 150 km 1x800 square millimeters cable, 175 straight and 225 cross-bonding joints and 96 outdoor terminations. Accessories will be provided by Pfisterer. Contract is expected to be signed in mid-April and the goods will be delivered in approximately 9 months. Fiberoptic cables, telecommunication and SCADA system as well as testing and training services will also be in Demirer Kablo’s scope.